Voor het vernieuwen van de conservering op de boogconstructie van de Muiderspoorbrug moest er een ingenieus concept worden bedacht.
Voor het vernieuwen van de conservering op de boogconstructie van de Muiderspoorbrug moest er een ingenieus concept worden bedacht.

From Texel to the Oosterscheldekering

In recent months, the Muiderspoorbrug between Diemen and Weesp has been firmly in the spotlight. Commissioned by ProRail, the distinctive railway bridge was scaffolded for a major protective coating project. NL Steigers devised an ingenious 200-metre-long platform, allowing the restoration work to be carried out without disrupting rail traffic. It shows just how specialised and inventive the company is: bespoke solutions are devised time and again to carry out complex work safely and efficiently. Across the Netherlands, from Texel to the Oosterscheldekering. Director Serdar Ort takes us through a number of notable projects.

An ingenious concept had to be devised to renew the protective coating on the arch structure of the Muiderspoorbrug. “During the Easter weekend of 2025, we had 104 hours during a possession to build a platform inside the bridge, 200 metres long and 13.5 metres wide, just above the overhead lines,” explains Ort. “

This platform served as a floor inside the arch bridge, making it possible to carry out the coating work safely without putting rail traffic at risk.” The wooden floor, fitted with steel guardrails, was designed and built entirely in-house by NL Steigers. “The materials were hoisted up from one side and carefully ‘run out’, resting on the cross-bracing just above the overhead line. The floor will remain in place for almost a year in total, as the next possession is not scheduled until 2026, when we can safely dismantle the platform.”

During a possession, NL Steigers built a platform inside the bridge, 200 metres long and 13.5 metres wide, just above the overhead lines.

Experience with bridges and locks

The Muiderspoorbrug is not NL Steiger’s only major project from the past year. The company has been involved in maintenance work on the Botlekbrug for many years. “We erect scaffolding here periodically to enable protective coating and maintenance work on the structure. We are also a regular partner to maintenance teams on other bridges and locks,” says Ort. “We recently worked on a lock in Amsterdam, commissioned by SPIE. Scaffolding and stair towers were installed to provide access to the reserve gate mechanism. At Sluis Lith, part of the weir complex on the River Meuse, we also provided scaffolding so that maintenance work on the chains could be carried out safely.”

Ingenious solutions

Earlier this year, NL Steigers completed another challenging job at Prinses Irenesluis in Wijk bij Duurstede: scaffolding was erected high up in the lock to remove asbestos panels. “As there was no room for large lifting equipment, every item of material had to be winched up individually, a logistical feat at a height of 40 metres,” says Ort. Smart solutions were also used in Zwolle, at Spoldersluis. “Here we erected suspended scaffolding from the quay, allowing vessels to continue passing unhindered during the renovation work. It is an example of how ingenuity and bespoke solutions help minimise disruption.”

Tholensebrug and Hubertustunnel

As well as locks and railway bridges, NL Steiger is involved in other major infrastructure projects. Ort says: “Brabotech is carrying out the concrete repairs required at Tholensebrug. We installed the scaffolding to provide access to the piers. While others opted for large-scale structures, we were able to offer a more efficient and safer alternative using stair towers and carefully positioned guardrails and toe boards.”

Another project NL Steigers has been working on over the past year is the renovation of the Hubertustunnel in The Hague, part of the Noordelijke Randweg. “The tunnel has been closed for major maintenance since 27 July 2025, and will remain closed until the end of April 2026 at the latest,” says Ort. “Commissioned by Strukton and other partners, we installed stair towers and scaffolding here, including around the piers and in the service building, where mobile elevating work platforms could not reach. We also erected a large tent to enable waterproofing work.” The project demonstrates the breadth of NL Steigers’ expertise, from railway bridges to motorway tunnels.

The list of projects is much longer. Scaffolding was erected on Texel and in Den Helder around the lifting mechanisms at ferry ports. Four small buildings housing the mechanisms were given protective coatings. Work on three has now been completed, and the fourth will follow shortly after bad weather caused delays. Work is also under way at the Oosterscheldekering. Scaffolding has been erected at various water-level monitoring stations to enable protective coating work, essential maintenance on one of the country’s most important flood defences.

The wooden floor, fitted with steel guardrails, was designed and built entirely in-house by NL Steigers.

In-house equipment

According to Ort, what all these projects have in common is the company’s approach. “We work with a relatively small, close-knit team of around 80 employees. That allows us to act quickly: we don’t need twenty people in the chain to get permission or approval.” The company also excels in creativity. It continually comes up with smart solutions to make work safer, faster or more efficient. All work is carried out using its own equipment, which is continually expanded and adapted. Whether it is a specially designed wooden floor for a railway bridge or suspended scaffolding from a quay, the aim is always to find the best solution for the situation.

With projects spread across the Netherlands and demand for bridge, lock and tunnel renovation and maintenance continuing to grow, Ort expects 2026 to be an extremely busy year. “Requests are already pouring in,” he says. This shows that the company’s expertise and ingenuity are increasingly recognised and valued across a wider range of sectors. Whether in Weesp, The Hague, Texel or the Oosterschelde, the common thread remains the same: safety, speed and smart bespoke solutions are the foundation. “Scaffolding is about much more than simply putting up a temporary structure. We make the Netherlands’ most complex infrastructure accessible.”

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectYearbook
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.