Composite access-track mat platform ‘floats’ on farmland

Final work is under way on the Oostpolder wind farm, in an agricultural area south of Eemshaven. The 21 wind turbines are being assembled in the middle of the fields at two pre-assembly sites. The two ‘platforms’, each measuring 100 metres square, were built using Ferex composite access-track mats. A sustainable and safe alternative to steel road plates that also leaves the soil undisturbed.

The new wind farm will consist of Enercon wind turbines. “These turbines are assembled on site in modules using a climbing crane,” explains Kees Wolbers, account manager at Ferex. “A major advantage of this construction method is that no special transport is needed to move the components. However, it does mean that a pre-assembly site, or in this case two, has to be set up on site to assemble the components. That is where Ferex came in.”

No ground preparation
The wind turbines, and therefore the two pre-assembly sites, are being built on farmland. “The farmers would not accept any disturbance of the existing soil to create the temporary pre-assembly sites,” says Wolbers. “Unlike steel road plates or dragline mats, composite access-track mats can be laid without any prior ground preparation. We can lay the mats directly on any type of ground, without first excavating the soil and creating a rubble track. Our composite access-track mats also form an extremely stable platform because they are joined on all four sides using a lapped joint. This keeps the platform intact even when heavy machinery is manoeuvring on it, while distributing the loads over a larger area. A 250-tonne crane and a 125-tonne crane are positioned on each of the 100-by-100-metre platforms to assemble the wind turbine components. Our mats therefore create a complete floor, including a safe ‘safety net’ beneath the crane.”

Using our composite access-track mats has halved the number of logistics movements on this project, says Wolbers. “This is mainly because the ground does not need to be disturbed. The large 4-by-2-metre size also means we can cover large areas in a short time. A total of 3,000 composite access-track mats were used for the two platforms on this project. Once the wind farm is complete, the mats will be removed and the farmers can get straight back to work in the fields. It is also gratifying for us at Ferex to see that our products can deliver significant CO2 savings during the construction of a project that is sustainable by design.”
The 21 wind turbines at the Oostpolder wind farm will have enough capacity to supply 50,000 households with electricity each year.