Collaboration and knowledge-sharing are the pillars of the ‘Zeven Kunstwerken’ project

De Noorder- en Zuidersluis in Schardam in het zomerse zonlicht.
De Noorder- en Zuidersluis in Schardam in het zomerse zonlicht.

Commissioned by Hoogheemraadschap Hollands Noorderkwartier (HHNK), the TAUW/Friso Civiel consortium (TFC) is currently working hard to improve the water safety of several structures in North Holland. This is the first project in the Netherlands to strengthen structures only, rather than dykes. Specifically, the work involves seven sluices that no longer meet the standard under the Flood Protection Programme (HWBP) and have consequently been rejected. Once the work is completed in autumn 2022, the sluices will once again be able to hold back water effectively. This will safeguard the safety of the hinterland for the future.

Following thorough procedural preparations and the granting of the various necessary permits, construction work is now in full swing. The Spuisluis Oostoever near Den Helder, the Sassluis in Enkhuizen, and the Hornsluis, Noordersluis and Zuidersluis in Schardam are being physically strengthened. “Based on the Water Act project plan, HHNK worked closely with the TFC consortium to establish a preferred option for each sluice as early as July 2019,” says HHNK project controls manager Karin Klein. “This means that a set of guard gates and four sluice gates will be replaced at Spuisluis Oostoever near Den Helder. Two additional sets of gates will be installed at the historic Sassluis in Enkhuizen. At the same time, two defective gates in the bypass culvert will be repaired. At the three historic sluices in Schardam, the existing gate will be replaced with a new two-part gate. The lower section is movable, allowing the sluice to be closed partially or completely. No physical works are planned at the flood barrier in Broekerhaven or the Grote Sluis in Hoorn. Here, we will only amend the closure protocol.” 

Een iconisch beeld van Enkhuizen vanaf de Sassluis.

Excellent collaboration

Throughout the project, the three partners are placing great emphasis on close collaboration and knowledge-sharing. This approach has led to exceptionally smooth transitions between project phases, rapid delivery and a genuine sense of working as one team. “This is the first project focused exclusively on improving the water safety of a number of structures in our area of management,” says Klein. “It is therefore a true pilot, in which we are working with specialist market parties in a unique way towards a shared goal. Everything is going entirely to our satisfaction. We would be keen to do more.” 

Dewatering the Zuidersluis in Schardam in preparation for strengthening works.

A unique project

The TFC consortium is carrying out the physical works, most of which are taking place along the shores of the IJsselmeer. Geert van der Linden, construction specialist and project manager for Friso Civiel (part of Friso Bouwgroep), describes the ‘Zeven Kunstwerken’ project as unique. “Because the contract was awarded to a consortium of an engineering consultancy and a contractor, we have been closely involved from the very outset. Together with our partner TAUW, we are working through every phase, from exploration to delivery. This approach is new to us, but it has a very positive impact on the final result and the project’s duration. The programme has remained unchanged since the exploration phase, meaning the sluices will be safe against flooding in Q2 2022.”

Specialisms

After the preliminary design was developed into a detailed design for construction, physical work on the project began in mid-October. According to Van der Linden, the varied scope of work is ideally suited to the TFC consortium. “Technically, what we are doing here is not very different from the other water engineering projects we work on. ‘It is net oars as oars’ (just like any other project, ed.),” says Van der Linden. What sets this project apart above all is the collaboration between client HHNK and the TFC consortium. “It is going exceptionally smoothly, including with the other partners working alongside us.     

A range of specialist expertise is needed to deliver this work successfully. To that end, we approached several parties at an early stage, each bringing the expertise and workforce required for a specific design. One of them is restoration contractor Jurriëns Noord (part of Friso Bouwgroep), which will restore the Sassluis and the sluices in Schardam. This work, like the rest of the project, calls for a carefully thought-out approach. After all, these are structures of considerable historical value. Careful work and thorough preparation are essential.”

A diver inspects the Sassluis in Enkhuizen in preparation for strengthening works.

Assessing the options

The TFC consortium developed the preferred options for each sluice, prepared the project plans under the Water Act and for the environmental impact assessment screening, and produced both the final design and the detailed design for construction for each sluice. “We assessed the possible solutions for each structure against one another, evaluating their feasibility, affordability and effects on the surrounding area,” says Anton van Essen, project manager and contract manager at engineering consultancy TAUW. “We also incorporated input from various stakeholders through intensive stakeholder management. This ultimately enabled us to provide a suitable response to our client’s requirements.”

Strengthening work begins at Spuisluis Oostoever.

A contractor’s eye for detail

Like Van der Linden, Van Essen describes the project as highly unusual. “Alongside our own knowledge and expertise, we were able to draw on Friso Civiel’s expertise from the exploration phase and carry it through the plan development phase and into construction. This meant we could assess the construction options with a contractor’s eye from the outset, and we received no objections to the permits required for the work. At the same time, we were able to address all possible risks in advance. On every front, starting early has paid off.” One good example is the dewatering of the five sluices that the consortium is working on during the plan development phase. This initiative made it possible to assess the condition of the structures accurately at an early stage, preventing uncertainties and risks in the final design. This benefits both construction and the end result.     

A business enquiry for Friso Civiel? Get in touch

Who worked on it

Zeven Kunstwerken

  1. contractorFriso Civiel
  2. engineering consultancyTAUW
  3. clientHoogheemraadschap Hollands Noorderkwartier (HHNK)
  4. restoration companyJurriëns Noord

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectZeven Kunstwerken
  • SubjectYearbook
  • CompanyFriso Civiel
  • CompanyTAUW | Consultancy and engineering firm
  • CompanyHoogheemraadschap Hollands Noorderkwartier (HHNK)
  • CompanyJurriëns Noord
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.