Tauw offers a way forward for halted construction projects following PAS ruling

Tauw offers a way forward for halted construction projects following PAS ruling

Following a successful ADC assessment carried out by Tauw, the land-use plan for the construction and widening of Kempenbaan-West in Veldhoven has been declared irrevocable. Many construction plans have been thrown into doubt by the earlier ‘nitrogen ruling’ by the Council of State. Tauw shows that a convincing ADC assessment may nevertheless offer a way forward for halted construction projects.

ADC assessment offers first successful way forward for Kempenbaan

For the reconstruction of Kempenbaan-West in Veldhoven, the Municipality of Veldhoven, working with Tauw, presented an alternative approach to nitrogen emissions to the Council of State. It showed that there are no better alternatives (A) to the reconstruction, that it serves an imperative (D) reason of overriding public interest and that the nature affected can be compensated for (C). “It is good to see that the Council of State is open to an ADC assessment that demonstrates the need for this project. The ban on the PAS will have disastrous consequences if the Council of State offers no alternative. Fortunately, the ADC assessment appears to provide a solution for necessary construction projects,” says Tauw project manager Frank Aarts.

Programmatic Approach to Nitrogen (PAS)

The Council of State’s ban on the PAS has direct consequences for ongoing permit applications and future project initiatives: these are temporarily put on hold and can no longer use the PAS at later stages of the process. The European Court of Justice previously indicated that a ‘programmatic approach’ is a suitable way to address the nitrogen issue. The ADC assessment can therefore offer clients an approach.

Een zakelijke vraag aan TAUW | Advies- en ingenieursbureau? Get in touch

Who worked on Kempenbaan-West

  1. ADC assessmentTauwIn this story
  2. municipalityVeldhoven municipalityIn this story
  3. steel structureBersselaar ConstructieMentioned in De Locht cycle bridge: a truss bridge in every sense

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ProjectKempenbaan-West
  • SubjectNews
  • CompanyTAUW | Consultancy and engineering firm
  • CompanyVeldhoven municipality
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.