Stikstof problems once again for infrastructure projects

Since the PAS was struck down by the courts in May 2019[1], the nitrogen crisis has continued to affect the civil engineering, infrastructure and construction sector. Recent Council of State rulings on the ViA15 Route Decision[2] show that nitrogen remains a live issue for infrastructure projects.
Criticism of the AERIUS Calculator
What was this ruling about? For an infrastructure project, the AERIUS Calculator must be used to determine the extent of any nitrogen deposition on habitat in a Natura 2000 site[1]. For traffic flows resulting from new projects, the calculator uses the SRM2 model. The OPS model is used for other sources and activities[3]. The SRM2 model calculates the effects of traffic flows up to a maximum of 5 kilometres from the source. It was then assumed that effects more than 5 kilometres away could no longer be meaningfully attributed to an individual project. The ruling of 20 January 2021 now makes clear that there is insufficient evidence to support ‘cutting off’ the effects of traffic flows at 5 kilometres. Effects at greater distances cannot be ruled out either.
This criticism is hardly surprising. For its own traffic measures to reduce nitrogen emissions, which were used to fill the ‘nitrogen bank’ for, among other things, MIRT projects[4], the national government determined and included positive effects at distances greater than 5 kilometres. The court has now given the national government an opportunity to provide evidence that the 5-kilometre limit cannot lead to an underestimate. It is possible, however, that providing such evidence will prove impossible.

Decisions once again at risk
In practice, this ruling means that ongoing infrastructure projects for which the AERIUS Calculator previously found no significant effects, or for which specific mitigation or compensation measures have already been determined, may not withstand a legal challenge. The traffic-related deposition for these projects may have been underestimated through the use of the SRM2 model, putting them at risk of suffering the same fate as the ViA15 in court.
Put things right in time
One possible way to avoid major delays is to carry out an additional calculation using the AERIUS Calculator for projects that do not yet have final, legally binding government decisions in place, this time using the OPS model for other sources. The OPS model can determine the effects of sources at greater distances too. If the new calculation shows effects, or greater effects, at greater distances than previously assumed, a suitable assessment may still be required, additional mitigation measures may need to be taken, or the ADC test may even have to be carried out, with compensation applied or increased. Even so, the principle still applies: it is better to anticipate than to react.
[1] ABRvS 29 May 2019, ECLI:NL:RVS:2019:1603 and ECLI:NL:RVS:2019:1604
[2] AbRS 20 January 2021, ECLI:NL:RVS:2021:105
[3] Under Article 2.1 of the Nature Conservation Regulation
[4] Road projects listed in Article 2.2 of the Nature Conservation Regulation