Project VIA15 | Pavement strength measurements to determine the right measures

QRoad provided GelreGroen with expert advice on the load-bearing capacity of the A15 and A12.
During the night, QRoad carried out FWD measurements, also known as falling weight deflectometer measurements, to determine pavement stiffness, remaining service life and the maintenance measures required.
Henk Jan Roeke, director of QRoad, explains the approach. “To establish the load-bearing capacity of roads, we simulate heavy wheel loads,” he says. “These heavy loads are, after all, the critical damage factor for pavements. With FWD measurements, we load the road surface and then determine the layer stiffness of the pavement and the subgrade.” QRoad’s work causes no damage to the road.
Accurate estimates
It took around fifty nights for QRoad to complete the measurements across all work sections of the A15 and A12. “To minimise disruption to traffic, the various activities for this project were combined and carried out in the evening and at night,” says Henk Jan Roeke. “As you often meet the same people, you build a friendly rapport. That certainly contributed to the excellent atmosphere on this project. Thanks to QRoad’s measurement data, GelreGroen now knows exactly how strong the existing roads are. It knows what measures need to be taken and how much it will cost to bring these roads back into top condition.”
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectNews