Privatisation of building control goes ahead

On 14 May 2019, the Senate passed the Quality Assurance (Building) Act by a large majority. A bizarre voting result. Both government parties, the CDA and ChristenUnie, voted against this landmark building legislation. The Act privatises building control. It also increases contractors’ liability and duty to warn.
The history of the Quality Assurance (Building) Act
CDA minister Donner drew up the outline of this building legislation in 2011. The CDA then voted in favour in the House of Representatives. As a right-wing party, it is understandable that the CDA supports privatising building control. GroenLinks voted against. In the Senate, the roles were reversed. How can a left-wing party in the Senate vote in favour of privatisation, while a right-wing party seeks to vote down legislation originating from its own ranks?
On 11 July 2017, the vote on this landmark building legislation was postponed at the request of former minister Plasterk. CDA senator De Vries-Leggedoor had doubts about the adopted amendments (changes to the legislation) tabled by PvdA MP De Vries. He had charged ahead like a bull in a china shop. His amendments increased both the contractor’s liability and duty to warn. He also gave municipalities greater powers to enforce the rules during and after construction.
No ‘night’ of De Vries
The CDA is very focused on contractors. This is hardly surprising, given that CDA members Elco Brinkman (now a senator) and Maxime Verhagen are the former and current chairs of Bouwend Nederland. Bouwend Nederland is far from enthusiastic about the building legislation, as it places a great many responsibilities on contractors. This criticism is justified. Half of all building defects are caused by the design of the building plans, which the contractor merely carries out. It was no surprise that the CDA voted against the legislation in 2017.
When the vote was postponed in 2017, neither the CDA nor ChristenUnie was in the governing coalition. Both are now. Since the CDA requested only six minutes of speaking time before the debate on 23 April 2019, it seemed the party had changed its mind after all. Over the previous two years, Minister Ollongren had clarified how the adopted amendments would be applied in several letters, in the hope of taking the sharpest edges off them. The minister also reached an administrative agreement with the VNG on privatising building control. However, the debate a few weeks ago made it clear straight away that the government party CDA would vote against. De Vries-Leggedoor began by expressing her appreciation for the minister’s efforts… The rest is history. The CDA and ChristenUnie were joined in voting against by the PVV and SP. So far, no surprises.
What was remarkable, however, was that GroenLinks, 50PLUS and Partij voor de Dieren voted in favour. All three had voted against the bill in the House of Representatives. Together with the VVD, D66, PvdA and OSF, they cast 42 votes in favour and 33 against. That was still a comfortable majority.
Privatising building control
It is better to assess the completed building against the building regulations than to assess the paper building plan. What matters is that the building itself is safe, not the paper plan. Municipalities will therefore no longer assess the paper building plan. Instead, a private quality assurance provider will check that the completed building complies with the requirements. The municipality may refuse permission to occupy the building if it does not receive a positive declaration from the provider. At present, municipalities are not required to carry out a final inspection.
A phased approach to privatising building control
Privatisation will be introduced in stages. First, the new system will apply to simple buildings such as homes, then to more substantial buildings such as schools, and finally to the largest structures, such as football stadiums. Many senators want the new system to apply immediately to more substantial buildings. The minister is right not to agree. It must first be demonstrated that the new system improves building quality for the lowest-risk buildings. However, quality assurance providers are likely to add most value on more complex, substantial projects, which the average municipal building control officer does not deal with every day.
Six months before the new system is due to apply to simple buildings, on 1 January 2021, at the same time as the Environment and Planning Act, the minister will assess whether the construction industry is ready for this change. On 10 May 2019, Minister Ollongren sent the Senate a letter explaining the circumstances in which she would actually privatise building control. This letter helped convince GroenLinks that the new system would be introduced only after a careful evaluation.
Municipal enforcement after the new building legislation comes into force
Municipalities will retain their powers to enforce the rules during and after construction. They will be able to enforce the building regulations on the basis of information from the quality assurance provider. Municipalities can also prevent the building from being occupied. They may do so if the quality assurance provider refuses to declare that the completed building complies with the building regulations.
There is a risk of duplication. In addition to the quality assurance provider, the municipality may also supervise construction. This increases the likelihood that municipal fees for obtaining the environmental permit (building permit) will not fall enough. The permit holder will also have to pay the quality assurance provider’s fees. There is a significant risk that the cost of building control will therefore rise. For the time being, the minister does not intend to force municipalities to reduce their substantial building permit fees. However, the overall cost of construction may still fall if the new system reduces the considerable costs contractors incur from errors and rework.
Bouwend Nederland’s objections are justified
The building legislation also increases contractors’ liability and duty to warn. Until now, contractors could not be held liable for defects that should have been discovered at handover: hidden defects. Under the new rules, contractors will remain liable after handover unless the defects are not attributable to them. Contractors must also warn the client in writing and unambiguously about errors in the design.
Bouwend Nederland is right to be critical that this places so many responsibilities on contractors. After all, half of all building defects originate in the design, and contractors will have to prove that they did not make any mistakes. Contractors are likely to take out more expensive liability insurance. These premiums, together with the cost of the quality assurance provider, will be passed on to consumers building a home.
At last, serious attention to building quality
It is a positive development that the passing of this building legislation finally brings serious attention to building quality. Research by Vereniging Eigen Huis shows that new-build homes have an average of 21 defects. That figure really must come down.
A mandatory final inspection of the completed building is a positive step, even if the inspection is carried out by a private quality assurance provider.
A separate environmental permit for a building-related technical activity under the Environment and Planning Act will also focus attention on building quality. Coincidentally, Elco Brinkman recently wrote in his memoirs that if he were still a minister, the Environment and Planning Act would never have been passed either. The CDA is not keen on change, even when improvements are clearly needed.