News

Levvel-bloc production facility officially opened in Harlingen

Levvel-bloc production facility officially opened in Harlingen

On Friday 27 September, construction consortium Levvel (BAM, Van Oord and Rebel) officially opened the production facility for Levvel-blocs in Harlingen. This is where the concrete breakwater elements are being produced to reinforce the Afsluitdijk over the coming years. Fokkens, a member of the Provincial Executive of Fryslân, performed the opening ceremony.

De video laadt pas als je op afspelen klikt.

Circular construction

Levvel has leased a site of around 10 hectares from Port of Harlingen at Lange Lijnbaan in the industrial harbour. It contains a shed of approximately 4,000m2, a carousel, a concrete batching plant, storage silos and depots for sand, gravel and cement, and a large gantry crane. The factory was built using circular principles: once production is complete, its components will be dismantled and reused elsewhere. Various regional companies have been involved in both the construction and the production process. Fokkens said: “The province is pleased to have a new factory in Fryslân producing such an innovative product. Because the Levvel-blocs are being produced close to the Afsluitdijk, in Harlingen, transport distances by water are short and the ecological footprint is small. This fits perfectly with the character of the Afsluitdijk. We are also pleased that so many regional companies have helped make this factory a reality, just as many companies in the region are now helping to reinforce the dike.”

Fully automated process

The Levvel-blocs are made using an automated carousel on which more than a hundred steel moulds rotate. This is a unique application in hydraulic engineering. The mould is filled with concrete and removed once the concrete has hardened. The empty moulds are inspected, cleaned of cement residue and prepared for the next pour. A Levvel-bloc is produced approximately every nine minutes, with at least a hundred blocs made each day.

Transport by water

The Levvel-blocs are moved through an opening in the shed by a large gantry crane to the adjacent storage depot. A basin has been built alongside the depot. The same crane loads the blocs onto vessels for transport to the Afsluitdijk. The blocs are also placed on the dike from the water, minimising disruption to road traffic.

A new outer layer

To reinforce the Afsluitdijk, a new outer layer is being added to the dike on the Wadden Sea side. No fewer than 75,000 Levvel-blocs will be installed over the existing basalt. The Levvel-bloc, also known as XblocPlus, was developed specifically for the Afsluitdijk. Each block weighs 6,500 kilos and helps reduce wave impact. The elements will have a rough upper surface and small pools where water can collect, creating opportunities for vegetation to grow. Their symmetry and regular arrangement give the blocks a calm appearance, reinforcing the dike’s clean, self-contained character.

The Levvel-blocs will deliver CO2 savings of as much as 56% compared with the preliminary design, because they require much less concrete than comparable dike reinforcement materials.

Afsluitdijk reinforcement

Construction consortium Levvel is working on the reinforcement of the Afsluitdijk on behalf of Rijkswaterstaat until 2022. Additional discharge sluices and pumping stations are also being built to increase the amount of water that can be discharged from the IJsselmeer into the Wadden Sea. This will ensure that the Netherlands remains protected against the power of the water in the future. For more information, visit www.deafsluitdijk.nl.

More information and Afsluitdijk information desk

Rijkswaterstaat, construction consortium Levvel, regional authorities (De Nieuwe Afsluitdijk) and Windpark Fryslân have jointly set up the “Loket Afsluitdijk”. It is the point of contact for all questions and suggestions about the work on the Afsluitdijk. T: 0800-6040 and E: [email protected].
More information about planned works is available at www.vanAnaarBeter.nl. More information about projects on the Afsluitdijk and the cycle bus timetable is available at www.deafsluitdijk.nl

Have a business enquiry for Van Oord? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectNews
  • CompanyVan Oord
Share this article

Follow on Grond/Weg/Waterbouw Nederland

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.