Good collaboration is essential to achieving an integrated approach

Project De Entree in Amsterdam is being delivered by Max Bögl & Partners. Iv-Infra is one of the partners, responsible for part of the design work and for ensuring the overall design solution is fully integrated.
The project involves many different disciplines and almost as many design firms. Take the construction of the underground bicycle parking facility, for example. This requires coordination between a considerable number of design firms: geotechnical engineering, structural engineering, electrical and mechanical services, architecture, and so on. The bicycle parking facility is part of the wider project and therefore also interfaces with designs for, for example, road infrastructure, public lighting, tram infrastructure, bridges, quays, cables and pipelines.
Phase 1: scope and execution requirements
It is clear that good collaboration between all the design firms is essential to achieving an integrated design solution. Careful thought was given in advance to how the design process should be organised to make this possible. The process was structured differently depending on the design phase. In phase 1 (Requirements Clash Analysis), the scope and requirements were reviewed in detail with the client, the municipality of Amsterdam, and all the design firms. The aim was to ensure that all parties involved had a clear and consistent understanding of the project parameters and expectations before design work began. The interfaces between the various designs were also identified during this phase.
Phase 2: final design
In phase 2 (final design), a single integrated design was developed. This involved extensive consultation to coordinate the technical details between the different parties. For example, one day a week was set aside for all the parties involved to work from the same location. All designs produced by the different parties were fully developed in 3D. BIM made it possible to identify clashes and demonstrate that interfaces were being managed.
Phase 3: construction design
In phase 3 (construction design), the integrated final design provided a basis for each discipline to further develop the construction design for its respective components. Throughout this process, checks were carried out to ensure that the development of the construction design did not deviate from the principles set out in the integrated final design. This made it possible to significantly reduce the frequency of meetings during the construction design phase. Any deviations from the final design were discussed at fortnightly integrated design meetings, where the parties assessed whether the changes had implications for components covered by other design disciplines in the project.