A new approach to procurement deserves a pat on the back

Innovation is not always about technology. Often, it is also about how we work. The province of South Holland can be proud of the new approach to procurement it is using for the Steekterbrug project. The approach is based on the DOEN method, which Rijkswaterstaat has already gained experience with, and has been adapted in some respects to the province’s way of working. We are keeping in touch with Rijkswaterstaat to exchange experiences for mutual benefit.
The project involves replacing the old Steekterbrug and falls under the responsibility of the province’s Steekterbrug core team. We spoke to the core team members about a new approach to procurement that brings about the necessary change from the traditional way of working.

The interviewees are Hans Schutjes, project leader, Eliane Scharten, stakeholder manager, and Marcel Kluter, contract and technical manager. All are members of the core team for the Steekterbrug Replacement project. Procurement for the work began in November 2019 and will continue until November this year. In the first quarter of 2020, work began on demolishing buildings and diverting a ditch, cables and pipes.
Selecting a contractor based on attitude and behaviour
Kluter opens the conversation: “With our new approach to procurement, we want to work very differently. We want to interact more with contractors, with two things at the heart of our approach. We want to embark on the design process together, strengthening the integration of the work and the design, and we want to select the contractor based on their attitude and behaviour.” We are told that this is underpinned by four objectives. Kluter continues: “You could call them ‘the four commandments’. First, we are aiming for optimal cooperation. Second, we want to prevent waste in every process, at all times. Third, the required quality must be delivered, with no compromises. And the fourth is also very important: the work must be done honestly, for a fair price.”
These four pillars are set out in the procurement process, and everything that is done is assessed against the four commandments. So how do you select the contractor, we ask. Kluter: “We issued a request for proposals containing only general information about the project itself. We did not include any drawings, requirements or design. We simply asked for a vision based on our requirements for working together. We received a number of vision documents, from which we selected five companies to proceed to phase two. Naturally, we also checked that those selected met the technical requirements and had sufficient experience in bridge construction.”
Phase two: assessment under independent supervision
The five selected companies were then assessed by consultancy Twijnstra and Gudde to determine their attitude and behaviour. Schutjes explains: “We designed exercises for this purpose. The first was hypothetical, while the second was based on the Steekterbrug project. There was no way to put on an act, as Twijnstra and Gudde monitored everything.” Kluter adds: “As a team, we also went through the assessment process. It sometimes led to emotional moments, both for the contractors taking part and for us. You are given a true reflection of yourself. That can be hard to take, but the aim is also to take a critical look at your own organisation. This was an unexpected benefit, and some good things came out of it. We didn’t do well as a team the first time around. We acted on that, and now we work more openly and honestly as a team, and share more.” Our conclusion is that the assessment itself already meets the four pillars. Kluter agrees. Scharten notes: “It was sometimes hard for the contractors to take too, but taking part in the assessments gives you much deeper insight into your own organisation.”

A question of trust
The Steekterbrug core team received only the scores from Twijnstra and Gudde for the final assessment. “So we don’t know what the contractors answered, we only see the final score. That allows us to remain impartial, and we have 100% confidence in Twijnstra and Gudde’s expertise.”
Schutjes continues: “A probity manager was also appointed, who in turn checks the assessments. Contractors can also go to him with their questions, as he acts as an ombudsman. Working this way keeps everything fair. We ask the contractor to provide their own justification for the budget, and we help out ourselves. The process was sometimes difficult for the contractors who took part in the assessments, as they are not used to it. We provided them with only the essential information they needed to proceed to the next phase.”
The choice has been made
Scharten: “Phase 3 of the process was the approach plan: how do you arrive at a design? Matters such as the process and risks are important here. We are currently in phase 4, the design phase and company formation, together with the preferred contractor. The contract has been awarded to the Heymans Hillebrand contractor consortium.” Kluter explains: “At this stage, it must be demonstrated that all the key objectives can be met in terms of budget, schedule and acceptable disruption, and that the design meets the required quality.”
The contract will be awarded in phase 5. “That is the construction stage, which also includes some design work,” says Scharten. Schutjes adds: “The risks must also be borne and kept within budget. This affects the organisation right down to the grassroots. People will really have to get used to working with us. But trust is the key word here too. This way of working also gives us scope for innovation. Asset managers are not brought in at the final stage, but are involved from the outset. In fact, this way of working is a great pleasure.”
Question about this story? Ask your question
Who worked on Steekterbrug
- contractors' joint venturecontractor consortium Heymans HillebrandMentioned in A new approach to tendering deserves a round of applause
- contractors' joint ventureHeymans HillebrandMentioned in A new approach to procurement deserves praise
- provinceprovince of South HollandIn this story
- concrete work and the road structureHeijmansMentioned in A state-of-the-art bridge, designed and built to meet all the latest standards and requirements
- movable bridgeHillebrandMentioned in A state-of-the-art bridge, designed and built to meet all the latest standards and requirements
Keep following this
Get an email when a new story is published. No account needed.
- ProjectSteekterbrug
- SubjectNews
- Companyprovince of South Holland