A mammoth task in central Amsterdam: De Entree project

A mammoth task in central Amsterdam: De Entree project
When Amsterdam City Council made its decision in 2017 to partner with Max Bögl & Partners on the redevelopment of the station area on the city-centre side of Amsterdam Centraal, one of the Netherlands’ most high-profile and complex infrastructure projects got under way. The aim of the project is to make the entire area easier to navigate and more attractive.

The work includes expanding the water area and building a new underground cycle park with space for 7,000 bicycles, renewing the tram tracks and stops and making them accessible to people with disabilities, and transforming the historic area in front of the central station into a welcoming space for pedestrians, cyclists and public transport users. It is a mammoth task for Max Bögl & Partners, but the companies working together are delivering the project successfully. The key word? Collaboration. Henk Jan Zoer, De Entree project manager at Max Bögl & Partners, explains.
“What we are building is not complex, but where we are building is”
“Anyone who knows Amsterdam knows what the area in front of the central station was like. It was always busy, with people going in and out of the station, lots of tourists, heavy bicycle traffic and trams coming and going. It has been car-free since 2018, but the number of people packed into every square metre seems only to be increasing. And all in a confined space,” Zoer begins. “Redeveloping the station area should make it easier to navigate and more liveable for everyone. The complexity of the work is due not only to having to divert people as they move around, but also to the interests of neighbouring stakeholders and the underground infrastructure. That is why Amsterdam City Council made project and stakeholder management a clear focus of the tender. What we are building is not complex, but where we are building is. The challenge was put to the market, with the aim of causing as little disruption as possible to stakeholders.”
Keeping the area functional
Max Bögl & Partners won the tender on the strength of its plans for delivering the project. “To keep the area functioning as well as possible, we have carefully planned the work in phases, dividing it into manageable work zones. We are also taking a range of measures to minimise disruption.
We had already involved our main partners during the tender, so everyone could contribute to the best approach. That meant we could hit the ground running,” says Zoer.
The partnership ethos is central to Max Bögl & Partners. Max Bögl specialises in concrete and steel construction, and its scope within the project team includes, among other things, marine works, surface works, track works and cable and utility works. “For each discipline, we carefully assessed which companies would be the best fit in terms of both the work and their working culture. Bringing these companies together as one team requires effective management. Each partner has both a shared and an individual interest in the project, so collaboration has to be excellent. To keep communication flowing, all the parties have access to the same software and up-to-date data. This includes 3D models, a document management system, requirements management databases and so on. For some of the companies, this was their first time working in this way.”

Adapting continuously to change
De Entree is being delivered under a UAV-GC D&C contract. According to Zoer, this calls for a particular mindset and a clear division of roles. “When you have been working together like this for four years, since the tender, you build a strong relationship and can usually understand each other with half a word. That is just as well, because the contract sum has since risen considerably. The additional scope includes countless changes, which require a great deal of flexibility from us and our partners. You have to be able to deal with the work constantly changing in nature,” says Zoer.
We ask what is driving this constant change. Zoer explains: “Among other things, it is down to stakeholders with additional requests, or particular interests that need to be taken into account. We also encounter surprises underground, because earlier contractors apparently improvised with cables and utilities that are not shown on the drawings or are in a different location from the one indicated. In short, we have to ‘make the impossible possible’, and usually we can. Traditional contractors would have thrown in the towel long ago. But by staying flexible and working together to find solutions, we refuse to let anything stand in our way. We are proud of that. We have a clear goal in sight as we head for the finish line.”
Safety for staff and the public
In Amsterdam, a permit to work in public spaces is granted only once a BLVC plan has been submitted and approved. Zoer says: “In the plan, we explain how we will manage accessibility, liveability, safety and communication around the works. The question we are constantly asking is how to ensure there is enough room within each work zone for all the disciplines to do their jobs, while still allowing all modes of transport to get through. It takes careful thinking to make the best possible arrangements for the surrounding area, while balancing the fact that this means creating multiple small work zones. How do you phase a project like this? And how do you start again when changes are made? There is only one solution: start with the big picture, then continually zoom in on the detail. This creates an ongoing dialogue between engineering and stakeholder management, and means we have to keep talking to each other. How much space do we take up? How do we create a suitable working area that is as safe as possible for staff and people nearby? All these questions come up when drawing up plans like this.”
Taking materials by water, as in the old days
De Entree requires large quantities of materials to be brought in and removed from site. To minimise disruption, deliveries and removals are scheduled outside peak hours wherever possible. “We have also chosen to transport materials by water wherever possible, much as they did in the old days. That avoids putting heavy axle loads on those charming little bridges. But, like everything on this project, water transport brings its own challenges. There are various ‘marine stakeholders’ on and around the water. The activity is just as intense there,” Zoer explains.

External collaboration matters too
Zoer explains that, alongside good collaboration within the team, external collaboration is also crucial. “There are formal stakeholders in this project, such as the parties responsible for the quay walls, the municipality, and the tram service, GVB. We work with them too. This places demands not only on our staff in management roles, but also on our site teams, who also deal with these stakeholders.”
Current works
At the time of writing, work is progressing at pace on the underground cycle park. “We have just pumped out the construction pit and started on the structural shell. The excavation measures around 100 metres by 85 metres, an enormous and impressive hole. We have also relocated the shipping companies to make it possible to build the cycle park in the central basin. We have had three tram possessions, which allowed us to complete the cable and utility works, surface works and track works in three sub-areas. Another great milestone this year was the opening of the Cuyperstrap.”
To conclude, Zoer says: “Everyone at Max Bögl & Partners working on this project is incredibly proud of what we are doing. The complexity of the work brings home to us every day just how important good collaboration and communication are. I am convinced that, once everything is complete, we will be talking about this project for a long time.”
The partners of Max Bögl Nederland B.V. on the De Entree project are:
Akson
Alom
Count & Cooper
Beens Groep
GEO2 Engineering
Goudappel Coffeng
Installatie Techniek Louwer
Iv-Infra
Knipscheer Infrastructuur
Kummler+Matter
Van den Heuvel
wUrck
Question about this story? Ask your question
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectNews
- CompanyCount & Cooper
- CompanyVan den Heuvel