1,500-ton bus and cycle tunnel moved into its final position

Between 4 and 7 April, Jan De Nul will move a new cycle and bus tunnel into position in the area around Kortrijk station, on behalf of Wegen en Verkeer West-Vlaanderen.
In recent weeks, Jan De Nul has built this 35-metre-long, 1,500-tonne tunnel off site, next to its final location. The operation to slide it into place will take 8 hours.
The new bus and cycle tunnel will connect the south side of the station with the town centre. Buses and cyclists will be able to pass through safely and without obstruction from car traffic.
8-hour sliding operation
Around midday on Easter Sunday, Jan De Nul will begin work on the tunnel. The ground beneath the tracks will be excavated, after which the tunnel will be jacked up and placed on rails. This will allow the 35-metre-long, 1,500-tonne tunnel to be slid into position. The sliding operation itself will take approximately 8 hours and will start on the morning of Tuesday 6 April.
From Wednesday 7 April, Jan De Nul will be able to backfill the excavation, allowing Infrabel to put the tracks back in place. From Monday 19 April, all trains will once again run over the refurbished tracks and through the new cycle and bus tunnel.
Jan De Nul will then connect the bus and cycle tunnel at both ends to the new underground car park beneath Conservatoriumplein on the north side, and to an approach ramp on the south side. Work on the cycle and bus tunnel will be fully completed by the summer holidays.