Smart phasing, maximum performance
Text Roel van Gils Image Boskalis

Rijkswaterstaat awarded Boskalis the contract in August 2023 to widen the A2 between the Het Vonderen and Kerensheide interchanges to 2×3 lanes plus a hard shoulder. In the tender, which placed considerable emphasis on the Most Economically Advantageous Tender (MEAT) criteria, the decisive factors were the approach to traffic disruption and the attention paid to the quality of life in the surrounding area, both during construction and once the road was in use. In short, smart phasing and maximum performance. This winning strategy came to the fore on a large scale for the first time in 2025 during the WeekendBreek: a historic weekend closure of the A2 in Limburg, bringing months of preparation together in 56 hours of intensive work.
“The key to our winning approach was smart phasing, based on a consistent programme of weekend working,” says Mark van den Hurk, tender and project manager at Boskalis. “Rather than imposing long-term traffic measures, such as narrowed lanes and barriers, we chose to carry out most of the work away from live traffic. Traffic will then be switched to the completely new carriageways on two occasions. This significantly reduces disruption for road users and the surrounding area. Traffic disruption and quality of life therefore carried considerable weight in the tender assessment. We achieved the maximum score in both areas: 10 out of 10. This made us highly competitive compared with the other bidders.”

Diverging Diamond Interchange
In its initial bid, Boskalis allowed for five full weekend closures of the A2, during which a large number of works would be carried out simultaneously along an 18-kilometre stretch. “The subsequent expansion of the scope meant that there were ultimately seven,” says Van den Hurk. “We combine as many works as possible during these weekends, minimising disruption to road users and the surrounding area at other times.” Another area in which Boskalis scored highly was its proposal to use a Diverging Diamond Interchange (DDI) on the local road network (N297) at the Born interchange. “By temporarily routing traffic over one viaduct while the other is demolished and rebuilt, we maintain optimal traffic flow and avoid long-term closures. This innovative solution has only been used a handful of times before in the Netherlands, including by Boskalis, and proved to be a differentiating feature of our bid.”

Intensive preparation
The first major closure of the A2 took place over the weekend of 14 to 17 November 2025. “Preparing for the WeekendBreek took virtually the whole year,” says project director Michel Bekooy. “In 2025, intensive work was carried out to prepare the route for construction: removing the peak-hour lane, relocating cables and pipes, detecting unexploded ordnance, conducting archaeological investigations and clearing vegetation. Badger setts were also relocated, which required extensive permitting procedures.”
WeekendBreek
The WeekendBreek was a historic moment for Limburg. “The A2, the province’s only north-south motorway, was closed completely for 56 hours over a distance of 18 kilometres. Long-distance traffic was diverted via Germany and Belgium, while regional traffic was routed via provincial roads. In collaboration with Rijkswaterstaat, a major communications campaign was launched to encourage people to work from home and use public transport,” recalls Alex Keur, civil engineering discipline lead. No fewer than 25 separate projects were carried out along the route during the WeekendBreek. “The emergency access route was a project in its own right, ensuring that emergency services could always get through. It proved its worth: response times were met and blood deliveries were able to continue. After the historic weekend, we received many compliments from emergency services and the local community about our traffic management. The challenge now is to repeat that success during the next six weekend closures.”

Building away from live traffic
This year, Boskalis is working on, among other things, the construction of wildlife crossings for Geoffroy’s bats, with seven planned in total. “Work on three began in the winter of 2025/2026 and they must be completed by 15 April, before the bats emerge from hibernation,” Bekooy stresses. The remaining four crossings will be built the following winter. “We are also starting work this year on rebuilding the Echt, Born and Urmond interchanges. Some of the new viaducts will be built alongside live traffic. During the next WeekendBreek in October this year, traffic will be switched over, allowing the remaining new viaducts to be built. This means the A2 will remain open for most of the works, and road users will barely notice the changes.”
Boskalis is building a total of fifteen new structures and underpasses to enable the A2 widening. Thanks to the phased, smart approach, traffic will be using large sections of the upgraded route well before its official completion in 2029.
Een zakelijke vraag aan Boskalis Nederland? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectRoad construction
- CompanyBoskalis Nederland