Platform on civil engineering, underground infrastructure, energy, construction equipment & construction machinery
The Green Bow goes for maximum reduction of CO2 emissions
Electric excavator.

The Green Bow goes for maximum reduction of CO2 emissions

"It's not there yet: zero emission. But we are already going for maximum reduction of CO2-emissions on the construction site." Speaking are Stefan van der Voorn, contract manager for Rijkswaterstaat and Sjoerd Gijezen, CSR manager for construction consortium De Groene Boog (which includes the companies Besix, Dura Vermeer, Van Oord, TBI (Mobilis, Croonwolter&dros), Rebel and John Laing). 

5 e CO2tainer mobile unit for charging various matter
The e-CO2tainer (archive image).

De Groene Boog is realizing the A16 Rotterdam project on behalf of Rijkswaterstaat. The A16 Rotterdam will be an 11 kilometer long energy-neutral national highway between the A16/A20 at Terbregseplein and the A13 at Rotterdam The Hague Airport. The new connection will ensure that traffic on the A13, A20 and surrounding local roads will soon be able to travel more smoothly and will contribute to improved mobility, accessibility and livability of the region. Together they talk about the green measures taken on the project.

2. HVO fuel
HVO fuel instead of diesel.

measures in a nutshell

Gijezen takes us through all the methods used to reduce CO2-drastically reduce emissions: "What is making a huge impact is the large-scale use of HVO fuel, accounting for 90% of CO2-reduction over diesel. 

HVO is extracted from residual materials from the food industry and can replace diesel 1 to 1. We have also commissioned a number of heavy (>20 tons) electric excavators. We also make use of the e-CO2tainer, a hybrid generator that contains both batteries and a clean generator. It can be used standalone, or hooked up to the grid to handle peaks. The e-CO2tainer jumps on only when needed, unlike traditional diesel generators, which are left running all day."

4. Electric roller
Fully electric roller.

'Electrification is great, but how do you provide power on site?'

That is the underlying question that had to be answered. Van der Voorn: "Do you bring the charger to the machine, or the battery to the charger?" Gijezen: "An electric crawler excavator is not made to travel long distances efficiently. Ideally, then, you bring the battery pack to the machine." Van der Voorn adds that the best way of working was considered for each location. "That is a continuous search, accepting that these kinds of issues require pioneering work. Gijezen: "There are many factors involved in answering that question per situation. What can be provided by the grid, what capacity does construction and electric equipment require, and in what locations is it physically possible and worthwhile to make charging facilities."

A perfect learning experience

There is a lot of talk in infra about alternative, clean energy sources to get and keep equipment rolling. This is the first time on a project of this size that maximum CO2-reduction by really scrutinizing everything when it comes to power. As such, Gijezen sees The Green Arc's approach as a perfect learning opportunity for future work. "We generate a blueprint that everyone can benefit from. Why keep reinventing the wheel?" A salient detail is that this green way of working was not in the tender. Van der Voorn: "De Groene Boog organized its own theme tables, in response to the overarching request from Rijkswaterstaat to be emission-free by 2030. From those theme tables, together with suppliers of green technology, we looked at where we could already give substance to Rijkswaterstaat's green ambitions in this project."

1. Electric 25-ton crawler excavator
An all-electric 25-ton crawler excavator on the construction site of The Green Bow.

More than fulfilling a promise

The Green Bow wants to go a step further, than just fulfilling Tender promises: "We want to excel. The Green Arch has established an EMVU fund (the U stands for implementation) and offered it to the Department of Public Works. Three million euros to pay for the sustainable measures from. So a good incentive. But in the end, how to proceed? The theme tables produced many insights and ideas. By sitting down with Rijkswaterstaat, experts and external parties, we came up with so many applicable measures that the three million euros were not enough. For that reason, we applied for additional support from the ministry. In June 2020, several proposals were submitted for this, including the electric equipment. In September 2020, we were awarded this contribution." Van der Voorn notes that due to good preparation, a very concrete proposal could be submitted. "In 2021 we went for a second round, that contribution was also awarded."

12. Visit outgoing minister Barbara Visser
Visit outgoing minister Barbara Visser on Nov. 8.

A learning process with necessary sacrifices

Gijezen sees it as a challenge to keep everyone "on board. "We run into some bumps, because we are treading the unbeaten path. But ... you learn mostly from the things that don't go smoothly. Then the trick is to keep motivating everyone so that we still reach the finish line together every time." According to Van der Voorn, in addition to a willingness to learn, that also requires effort "We stick our necks out in several areas," he says. "The mindset has to be right, the noses have to be in the same direction. That requires a lot of persuasion from The Green Arc and decisiveness from Rijkswaterstaat. We know that what is being done now is a catalyst for future projects. That is why it is so important that everyone participates and continues to participate. We show that it can be done and that has a flywheel function. Realistically, we are far from being there yet, but we are paving the way to 'better and better'."

In conclusion, Gijezen says, "We see where we need to go. To achieve a goal over time, the front-runners need to be encouraged now. We have to realize that what we do now will be a requirement in 2030. And that's not that far away."     

"*" indicates required fields